- Pipejacking in Aldershot
A UTX was completed this month in the Ash Vale area of Aldershot to install a new sewer for Thames Water. Delta CE subcontracted the work from MGJV and successfully installed the DN600 pipe using an Iseki Unclemole. Delta CE worked in parnership with Marbro Contractors to deliver this project
.
...
Read More - Completed Shaft - Claverdon STW Pump StationWork was completed today on the construction of a 6m ID shaft at Claverdon STW. The shaft will be used as a pumping station as part of the upgrade of the works.
Read More - Perforator goes to Work
Work has started on a new sewer requisition in Crawley including trenchless installation of DN225 pipe utilising Delta's PBA 85 guided auger boring system.
...